Precedence time critical path

Propagate earliest finishes while allowing independent tasks to overlap.

Adult planning suggestion: about 9–12 · Logic & rule checking

Players
2–3 per group
Time
15–25 minutes
Materials
Five duration cards and dependency table.

Prepare

Tasks last A=3,B=2,C=4,D=2,E=1 time units. A and B may start at time 0. C requires A; D requires both A and B; E requires both C and D. There is no shared-worker limit or switching cost in this model.

Follow the rule

For each task, earliest start is the maximum finish of its immediate predecessors, or zero if none. Earliest finish is start plus duration. Compute only after all predecessor finishes are known. Do not add independent branches as though one worker must execute them serially.

Check each step

A finishes at 3 and B at 2. C runs 3–7. D starts at max(3,2)=3 and finishes at 5. E starts at max(7,5)=7 and finishes at 8. The end-to-end controlling chain is A,C,E, totaling eight units.

Worked example

Now delay D's start to 5 without changing anything else. D finishes at 7 and E can still start at 7. A later start of D would delay E. Compare this explicit change with the original schedule instead of assuming every task has zero flexibility.

Finish and adapt

Ten trios can choose tasks, calculate times and audit prerequisites. Stop when each interval and the completion time is checked. If adding a single-worker constraint later, announce a new problem: the eight-unit result no longer promises feasibility. Do not treat this paper model as a real construction plan.

Purpose, observation and provenance

Within this activity: Propagate earliest finishes while allowing independent tasks to overlap.

Observe whether the player uses max at a join rather than summing predecessors.

Our rules, examples and printable diagrams are separately prepared. The earliest inventor of the broader mechanism is not established here.

MIT OCW — Critical Path Method — Technical scheduling lecture; our five-job arithmetic model assumes unlimited parallel resources and is not an age-validation study.

Secondary practice: Cooperation and explaining a check.

For a class of 30, use ten groups of three. Prepare one player-material set per group and keep the host key with the adult. Rotate operator, recorder and checker after each worked example; a reader or scribe may help without choosing answers. Avoid public ranking or diagnostic labels.

Age bands are planning suggestions. Background references may address older learners and do not validate suitability for this age band. Goals describe observable actions, not measured long-term gains or institutional endorsement.

Free alternative: Copy the supplied grids, labels and cards onto reused paper. No specialist product is needed. Adults may prepare pieces or act as a scribe.

Printable materials

Preview at 100% scale, with browser headers and footers off. Cut with suitable help. Keep host keys separate. This is a manual tabletop kit, not an online opponent, automatic judge or solver.

Precedence time critical path · Player materials

Before you start

Tasks last A=3,B=2,C=4,D=2,E=1 time units. A and B may start at time 0. C requires A; D requires both A and B; E requires both C and D. There is no shared-worker limit or switching cost in this model.

For each task, earliest start is the maximum finish of its immediate predecessors, or zero if none. Earliest finish is start plus duration. Compute only after all predecessor finishes are known. Do not add independent branches as though one worker must execute them serially.

TaskDurationAfterStartFinish
A3—
B2—
C4A
D2A,B
E1C,D
Controlling chainDelay D start to 5: effect?
________________
________________
________________

Precedence time critical path · Host key — keep separate

A 0–3; B 0–2; C 3–7; D 3–5; E 7–8. D may instead run 5–7 without delaying E.

Run and audit

Tasks last A=3,B=2,C=4,D=2,E=1 time units. A and B may start at time 0. C requires A; D requires both A and B; E requires both C and D. There is no shared-worker limit or switching cost in this model.

For each task, earliest start is the maximum finish of its immediate predecessors, or zero if none. Earliest finish is start plus duration. Compute only after all predecessor finishes are known. Do not add independent branches as though one worker must execute them serially.

A finishes at 3 and B at 2. C runs 3–7. D starts at max(3,2)=3 and finishes at 5. E starts at max(7,5)=7 and finishes at 8. The end-to-end controlling chain is A,C,E, totaling eight units.

Now delay D's start to 5 without changing anything else. D finishes at 7 and E can still start at 7. A later start of D would delay E. Compare this explicit change with the original schedule instead of assuming every task has zero flexibility.

Ten trios can choose tasks, calculate times and audit prerequisites. Stop when each interval and the completion time is checked. If adding a single-worker constraint later, announce a new problem: the eight-unit result no longer promises feasibility. Do not treat this paper model as a real construction plan.

Observe and support

Observe whether the player uses max at a join rather than summing predecessors.

Use large paper marks or a scribe when needed. A valid example is not a uniqueness or long-term learning claim.