Order Jobs through Two Workstations
Choose one shared job order that reduces the time until both stations finish.
Adult planning suggestion: about 9–12 · Logic & rule checking
- Players
- 3 with an adult facilitator
- Time
- 15–25 minutes
- Materials
- Printed player sheet or copied paper, pencil and small counters.
Prepare
A needs 2 then 6 units; B needs 5 then 1; C needs 3 then 4. Each job visits station 1 then 2. Each station handles one job at a time.
Follow the rule
Find the smallest remaining duration across both stations. If it is at station 1, assign that job to the earliest empty position; otherwise assign it to the latest empty position.
Check each step
For each order write station 1 finish times. A job may start at station 2 only after its first operation and the previous second operation finish.
Worked example
Compare A,C,B and B,C,A. Keep a row for waiting time so an idle station is visible.
Finish and adapt
Finish with the final completion time for both schedules. Check all six orders to confirm the minimum for this example.
Purpose, observation and provenance
Within this activity: Choose one shared job order that reduces the time until both stations finish.
Ask the checker to point to the move or calculation that decides the outcome.
Our rules, examples and printable diagrams are separately prepared. The earliest inventor of the broader mechanism is not established here.
Johnson’s two-machine rule — Rule or mathematical background for our original paper exercise. The small example and end condition are ours.
Secondary practice: Cooperation and explaining a check.
For a class of 30, use ten groups of three. Prepare one player-material set per group and keep the host key with the adult. Rotate operator, recorder and checker after each worked example; a reader or scribe may help without choosing answers. Avoid public ranking or diagnostic labels.
Age bands are planning suggestions. Background references may address older learners and do not validate suitability for this age band. Goals describe observable actions, not measured long-term gains or institutional endorsement.
Free alternative: Copy the supplied grids, labels and cards onto reused paper. No specialist product is needed. Adults may prepare pieces or act as a scribe.
Printable materials
Preview at 100% scale, with browser headers and footers off. Cut with suitable help. Keep host keys separate. This is a manual tabletop kit, not an online opponent, automatic judge or solver.
Order Jobs through Two Workstations · Player materials
A needs 2 then 6 units; B needs 5 then 1; C needs 3 then 4. Each job visits station 1 then 2. Each station handles one job at a time.
Find the smallest remaining duration across both stations. If it is at station 1, assign that job to the earliest empty position; otherwise assign it to the latest empty position.
For each order write station 1 finish times. A job may start at station 2 only after its first operation and the previous second operation finish.
| Job | A | B | C |
|---|---|---|---|
| Station 1 | 2 | 5 | 3 |
| Station 2 | 6 | 1 | 4 |
| Step / cell | Decision / value | Rule checked |
|---|---|---|
| ________ | ________ | ________ |
| ________ | ________ | ________ |
| ________ | ________ | ________ |
| ________ | ________ | ________ |
Order Jobs through Two Workstations · Host key — keep separate
A,C,B finishes at 13; B,C,A at 18. Johnson’s rule puts B last, then A first, leaving C in the middle.
Lead and check
A needs 2 then 6 units; B needs 5 then 1; C needs 3 then 4. Each job visits station 1 then 2. Each station handles one job at a time.
Find the smallest remaining duration across both stations. If it is at station 1, assign that job to the earliest empty position; otherwise assign it to the latest empty position.
For each order write station 1 finish times. A job may start at station 2 only after its first operation and the previous second operation finish.
Compare A,C,B and B,C,A. Keep a row for waiting time so an idle station is visible.
Finish with the final completion time for both schedules. Check all six orders to confirm the minimum for this example.
Classroom: ten trios for 30 learners; one kit per trio. Rotate operator, recorder and checker. Age guidance is a planning suggestion; prerequisite support may be necessary.